Texas adopted the 2026 National Electrical Code (NEC) on September 1, 2026. Any electrical permit applied for on or after that date must meet the 2026 edition. For water and wastewater facilities, the changes that matter most affect arc-flash labeling, generator and standby power, load calculations, and how SCADA and low-voltage systems are installed.
The most vulnerable projects are those designed under the 2023 code that still haven’t been granted permits. A plan drawn last year can get flagged in review this year. Here’s what changed, what it means for treatment plants, lift stations, and pump stations, and what owners should do about it now.
When did Texas adopt the 2026 NEC® and which projects does it apply to?
The Texas Commission of Licensing and Regulation voted unanimously on July 28, 2026, to adopt the 2026 NEC®. It became the statewide minimum standard on September 1, 2026, for cities and unincorporated areas. Permits applied for on or after that date must comply with the 2026 edition.
Cities can still set their own permitting rules and adopt local amendments. Before a design is final, confirm with the Authority Having Jurisdiction (AHJ) which amendments apply. Houston, San Antonio, and a small city in the valley may not each handle it the same way.
What changed for arc-flash labels?
Under Section 110.16, arc-flash labels are now required on more equipment and have to carry more information. The old size threshold for service and feeder equipment is gone. Switchboards, switchgear, enclosed panelboards, motor control centers (MCCs), and other equipment likely to be serviced while energized all need a label.
Each label now has to show:
Nominal system voltage
Arc-flash boundary
Available incident energy or the required PPE
The date the arc-flash assessment was completed
Labels also have to be permanent, whether they’re applied at the factory or in the field.
The date requirement is also a key factor to watch. Operators at water and wastewater plants work on energized equipment to keep treatment processes running smoothly. A dated label shows everyone how old the study behind it is. If a plant has added pumps, replaced a transformer, or seen the utility change its service since the last study, that label may no longer match the equipment. Section 110.24 still requires service equipment to be field-marked with the maximum available fault current and the date the calculation was performed.
We recommend putting the arc-flash study and labeling in the electrical contractor’s scope, with clear ownership by the same team purchasing, measuring, and installing electrical equipment. Leaving it to “the contractor will handle it” is how labels end up missing at final inspection.
GE recommends that every project that modifies an existing electrical system, installs a new power system, or has rehabilitation include a standard power system arc flash study as part the contractor’s scope of work. Article 130 calls for the energy analysis to be performed no later than every 5 years.
What changed for generators and standby power?
Several updates landed in Article 445 (generators) and Article 700 (emergency systems), with parallel changes in Article 701 (legally required standby) and Article 702 (optional standby). For facilities that depend on standby power, these are the ones to check first:
Remote shutdown. Generators over 15 kW now need a clearly marked remote shutdown device outside the equipment room. It has to disable the start circuits and require a mechanical reset (445.19).
Transfer equipment. Language about “redundant” transfer equipment has been replaced with bypass and isolation equipment. Manual bypass needs a qualified person actively supervising (700.6(C)).
Portable generator connections. Emergency systems with a single alternative power source must now include a permanent, interlocked switching mechanism with overcurrent protection during maintenance or repair (700.4(F)).
Load shedding. Optional standby systems can now use an energy management system to shed loads automatically and manage generator capacity (702.4(A)(2)).
A sewage surge story that shows why these changes are important.
On May 28, a storm knocked out power at a New Braunfels Utilities wastewater facility for about three hours. With the lift station unable to move flow, roughly 550,000 gallons of untreated wastewater reached the Guadalupe River, and the Texas Commission on Environmental Quality opened an investigation. The changes above cover the equipment that keeps a station running through an outage like that, how generators start and shut down, how transfer switches get serviced, and how load gets managed when standby capacity is tight.
Do I need a new selective coordination study?
If you’re modifying an emergency or legally required standby system, yes. Section 700.32 now requires selective coordination to be re-evaluated when overcurrent devices are replaced or when the system is modified—and a licensed Professional Engineer (PE) has to document it. Swapping breakers in a Motor Control Center (MCC) or adding a generator is enough to trigger it.
How does the 2026 NEC® affect SCADA, security, and low-voltage installations?
Chapter 7 was reorganized around one framework for all limited energy systems. New Articles 720 through 723 cover general requirements, power sources, cables, and raceways. Article 725 shrank to a few sections, with its rules moved into the new articles. Chapter 8 changed too: interior communications wiring now follows Chapter 7, and Chapter 8 only covers systems outside and entering buildings.
At a water or wastewater facility, this covers SCADA networks, instrumentation wiring, fiber, cameras, access control, and intrusion systems. Those scopes often sit with different trades: the integrator, the security contractor, and the electrical contractor. Specs that still cite old Article 725 or Chapter 8 sections are out of date. Update the spec references and define who owns each piece before the bid process, not during commissioning.
This is one reason we design electrical, SCADA, and security systems under one roof. When one team draws all three, the drawings agree with each other.
What should project teams do now?
Every engineering firm should have as part of their design scope to verify current jurisdiction NEC version to support modifications in their design to comply with the new guidelines.
Check local AHJ (Authority having jurisdiction) to verify if they have also standardized on the new NEC version. Any jurisdiction that has adopted the new version should plan to redo their arc flash study and ask notify their design engineering firms of the change.
Update specifications that cite 2023 section numbers (220 to 120, 750 to 130, 725 to 720 through 723).
Put the arc-flash study and labels in the design and closeout scope, with a named owner.
Re-check generator, transfer switch, and coordination design against Articles 445, 700, 701, and 702.
Ask the AHJ about local amendments before the design is final.
Where Guzman Engineering Fits In
Guzman Engineering designs electrical, SCADA, and security systems for water and wastewater facilities across Texas—spanning from Houston and the IH-35 corridor to Dallas, San Antonio, and the Rio Grande Valley. We work with cities, utilities, and civil engineering firms that bring us onto their teams. If you have a project in design or awaiting a permit, we can review it against the 2026 NEC® and tell you what needs to change before it costs you a resubmittal. Talk to our team at https://www.guzmaneng.us/contact.